Mixed Waste Management Facility, Monthly Report June 1994
Author | : |
Publisher | : |
Total Pages | : 30 |
Release | : 1994 |
ISBN-10 | : OCLC:1066028797 |
ISBN-13 | : |
Rating | : 4/5 (97 Downloads) |
Book excerpt: This monthly report for June 1994 presents general progress in the development of the MWMF including bugetary considerations. During June, the outstanding issues of Project guidance and OPEX/CENRTC funding were essentially resolved. A letter from DOE/OAK on June 28 provided the KD-1 decision and provided revised scope and budget guidance for the Project. Prior to this, during June, an agreement with DOE for release of funds to mitigate the OPEX/CENRTC funding levels was also completed. In response to KD-1 guidance, work to provide a revised Project schedule and budget profile began. Preliminary design activities have been on hold since May 1.